PROJECT STATUS:
This project is completed!
The Branch Hill-Guinea Pike widening project was completed in a series of coordinated phases.
Phase 1: June 4, 2018 through July 20, 2018 
Click to view the project map for Phase 1
Phase 2: July 20, 2018 through Sept. 15, 2018 
Click to view the project map for Phase 2
Phase 3: Sept. 15, 2018 through end of 2019
Final phase of work: Signal installation and activation – Spring 2019
|