PROJECT SCOPE:
New left turn lanes have been added in each direction on Shayler Road at Bach-Buxton Road. New traffic signals also were installed to facilitate more efficient traffic movements in this area.
|
CONSTRUCTION TIMING:
Completed
|
COMMUNITY BENEFIT:
Improving safety and the flow of traffic at this intersection is a significant priority with the increased traffic moving through this area with the newly-constructed West Clermont High School. New turn lanes and updated signals help traffic move more smoothly through the intersection of Bach-Buxton and Shayler Road. These improvements also support the work being done at Clough Pike and Bach-Buxton Road.
|
CONSTRUCTION COST:
$615,000
|