Project StatusThe Branch Hill-Guinea Pike widening project will be completed in three phases: Phase 1 is expected to last approximately seven weeks, from June 4 through July 20.During Phase 1, work will take place on northern end of Branch Hill-Guinea Pike and Cook Road. A detour will be put into place for through traffic. Access within the project area will be maintained for local property owners only. Permissible traffic movements during this phase will be:
Phase 2 is expected to last approximately eight weeks, from July 20 through Sept. 15.During Phase 2, work will take place on the southern end of Branch-Hill Guinea Pike and Weber Road. A detour will be put into place for through traffic. Access within the project area will be maintained for local property owners only. Permissible traffic movements during this phase will be:
The final phase of work will take place from Sept. 15 through the fall, but will not result in full-time road closures.All roads will be reopened to through traffic with only minor temporary closures taking place as crews complete the final components of the project. |